Tata Steel secures £500M from UK government for green steel project at Port Talbot

Tata Steel has signed an agreement with the UK government over a £500 million grant for its £1.25 billion green steel project at Port Talbot, designed to transform the future of the steelmaker into greener methods of production. It will be operational within three years and secure 5,000 jobs. An announcement was made on September 11 after months of negotiations with the Labour administration.

Tata Steel

 Green Steel Port Talbot

This grant will facilitate Tata Steel's plans to replace the old-fashioned blast furnaces in Port Talbot with electric arc furnaces, or EAFs, that run on recycled steel. This is part of Tata Steel's overall roadmap to cut carbon emissions and meet the objectives of sustainable production. Modernization of the process will further help in efficiency gains along with the reduction of emissions.

However, the new furnaces need fewer men, which translates to the loss of 2,800 jobs. The Tata Steel Company has now given an assurance to those who are about to lose their jobs that this will be given the "most generous support package" it has ever given, with pre-retirement redundancy pay, retention bonuses, and extensive re-skilling programs that will better prepare them for alternative job opportunities.

Tata Steel

Government's Role and Support for Workers

UK Business Secretary Jonathan Reynolds welcomed the improvements in the deal secured during the Labour administration. "This improved deal goes beyond what the previous government had agreed to, with a minimum of £15,000 voluntary redundancy payout and a £5,000 retention payment. Paid-for training and re-skilling will also ensure workers can move into future job markets," Reynolds said.

Commenting on this development, Tata Steel Managing Director T.V. Narendran said, "We are thankful to the UK Steel Committee and the government for their support and look forward to the efficient execution of the Electric Arc Furnace project."

Tata Steel

Timeline and Job Creation

Basic engineering for the project is already complete, and Tata Steel expects to begin large-scale site work by July of 2025. Equipment orders for the EAF will be placed shortly. The company foresees the creation of up to 500 new jobs during the construction period in support of the switch to electric furnaces.

Tata Steel

Future Steel Investments

Apart from the steel project in question, Tata Steel pledged to "continue to work closely" with the government on future investments in the steel sector, considering opportunities for "further innovation and growth". It promised to support workers who were made redundant with training schemes, which would be paid for, while keeping the staff on full salary for the first month and £27,000 a year for the rest of the scheme.

Inputs by Agencies 

Image Source: Multiple Agencies 